The Process
Steps once there is a verbal acceptance of the Project Proposal
Contracts
2-3 days
Engineering
2-3 weeks
Choose Tile & Exterior Finishes
Client to finalise these choices
Contractors Engaged
Fencing Contractors, Licensed Electrical & Plumbing Contractors are engaged.
Permit
2-3 weeks
Start Build
Start once we receive permit
Shell installed
7-10 days
Milestone Content goes here
Pool Pipes
Run pool pipes over the next 7-14 days
Start Landscaping
Landscaping begins
Licensed Plumbing & Electrical Works
Licensed Plumbing & Electrical Works are installed---Gas Meter will require up grade
Tiling
Tiling of Pool Prior to Paving/Coping Installed. 7-10 days
Landscaping completed
Landscaping completed
Equipment installation
Equipment installed & checked
Pool Fencing
Pool fencing installed & inspected by the Building surveyor
Pool Filled
Pool filled & commissioned.